SME Times is powered by   
Search News
Just in:   • How EU-India FTA goes beyond tariffs to strategic trust  • Crude oil prices fall up to 2 pc, head for steep weekly losses  • India, UK explore new opportunities to deepen economic, trade cooperation: Piyush Goyal  • Amazon’s $48 billion investment in India to create new opportunities for youth: PM Modi  • "A Call for AI Democracy: Nadella Warns Against Concentrated Power" 
Last updated: 22 Sep, 2021  

Karnataka Map THMB K'taka CM sets deadline for B'luru Metro 2nd phase completion

Karnataka map
   Top Stories
» How EU-India FTA goes beyond tariffs to strategic trust
» India, UK explore new opportunities to deepen economic, trade cooperation: Piyush Goyal
» Amazon’s $48 billion investment in India to create new opportunities for youth: PM Modi
» 11th BRICS Energy Ministers' meet to be held in Gurugram today
» PM Modi reviews Rs 30,000-crore infra projects, stresses faster execution
SME Times News Bureau | 22 Sep, 2021
Karnataka Chief Minister Basavaraj Bommai has set a deadline for Bengaluru Metro Rail Corporation Limited (BMRCL) to complete two phases of Metro work in the city by 2024.

After participating in a function organised to mark the breakthrough of the tunnel boring machine (TBM) Urja at Shivajinagar Metro Station, Bommai on Wednesday said 56 kilometre of the Namma Metro network will be available to the people after the completion of the two phases.

After the completion of three phases, Metro services will become the lifeline of the city, he added.

"I have spoken to authorities to complete the two-phase work by 2024 though the original deadline is 2025. The plan has been reworked and rescheduled. I have asked BMRCL to speed up work as commuters are suffering. Once the project is completed, a large number of people will switch to Metro and there will be less traffic on the roads," Bommai said.

The TBM (Urja) was given a start by former Karnataka Chief Minister B.S. Yeddiyurappa on July 30, 2020 at the Cantonment station.

After completing 855 metre of tunnelling, the breakthrough at the north end of Shivajinagar station took place on Wednesday.

TBM (Urja) started laying the first tunnel ring on August 20, 2020 from Cantonment station and successfully tunnelled up to Shivajinagar station.

Tunnelling using TBM is the most advanced PLC-based technology but operation of such machines with high precision needs highly skilled manpower and experts in the field.

The TBM will then be disassembled, transported by road to the launching shaft at north end of Cantonment station, where it will be reassembled and commissioned to construct a tunnel between Cantonment and Pottery Town station in Bengaluru.
 
Print the Page
Add to Favorite
 
Share this on :
 

Please comment on this story:
 
Subject :
Message:
(Maximum 1500 characters)  Characters left 1500
Your name:
 

 
  Customs Exchange Rates
Currency Import Export
US Dollar
₹95.3
₹93.6
UK Pound
₹127.7
₹123.7
Euro
₹110.65
₹106.9
Japanese Yen ₹59.75 ₹57.9
As on 24 Jun, 2026
  Daily Poll
What’s your biggest challenge with the 45-day payment rule?
 Corporates canceling our orders
 Clients demanding longer credit anyway
 Strained business relationships
 Filing complaints kills future work
 No issues, cash flow has improved
  Commented Stories
 
 
About Us  |   Advertise with Us  
  Useful Links  |   Terms and Conditions  |   Disclaimer  |   Contact Us  
Follow Us : Facebook Twitter