Key Expressway in Uttar Pradesh to open in December
|
|
|
|
Top Stories |
|
|
|
|
SME Times News Bureau | 10 Jul, 2019
The second section of the
Delhi-Meerut Expressway, from UP Gate till Dasna in Ghaziabad, is set to
be commissioned in December this year, about five months ahead of its
scheduled completion date.
According to the National
Highways Authority of India (NHAI), work on the project is 55 per cent
complete and will be finished ahead of the targeted May 2020.
The
ambitious Expressway has been conceived to provide seamless travel from
Delhi to Meerut as well as Hapur in the prosperous western Uttar
Pradesh.
Once it is operational, motorists from Delhi will be able to reach Meerut in just one hour, NHAI sources said.
The
Expressway's first section, from Sarai Kale Khan in Delhi to UP Gate in
Ghaziabad, was completed in June 2018 and it was inaugurated by Prime
Minister Narendra Modi.
The 59.78 km stretch from Delhi to Meerut will be a six-lane double carriage Expressway and can be used after paying toll.
Along
this stretch, the distance from Sarai Kale Khan to Dasna will be
flanked by four lanes of roads on either which will remain free for use
by commuters.
The 22.23-km stretch from Dasna to Hapur will be a
six-lane road flanked by two service lanes on either side that will also
be free for commuters. Only around 5 per cent of construction work
remains to be completed on this stretch.
"There will be three
toll plazas along the e-way. It will have three entry and exit points
between Sarai Kale Khan and UP Gate. Three more entry and exit points
will be provided in Ghaziabad between UP Gate and Dasna," a senior NHAI
official told IANS.
The section from UP Gate to Dasna, which
falls entirely within Ghaziabad, has a couple of issues that has been
delaying its progress.
"A water pipeline near Pratap Vihar in
Ghaziabad has to be shifted. Also, a Delhi Municipal Corporation toll
kiosk that is causing congestion at UP Gate needs to be shifted. We are
in talks with the authorities to expedite these works," said the
official.
The 31.78-km stretch of the Expressway from Dasna to Meerut, which is the final leg of the project, is 52 per cent complete.
Work
on four kilometres of this particular stretch has been held up owing to
arbitration issues raised against land acquisition by farmers. About
0.48 hectares of land along this stretch is also awaiting forest
clearance.
The stretch between Dasna and Hapur, which is not part of the Expressway and which will be toll free, is 95 per cent complete.
|
|
|
|
|
|
|
|
|
|
|
|
|
Customs Exchange Rates |
Currency |
Import |
Export |
US Dollar
|
66.20
|
64.50 |
UK Pound
|
87.50
|
84.65 |
Euro
|
78.25
|
75.65 |
Japanese
Yen |
58.85 |
56.85 |
As on 13 Aug, 2022 |
|
|
Daily Poll |
|
|
PM Modi's recent US visit to redefine India-US bilateral relations |
|
|
|
|
|
Commented Stories |
|
|
|
|
|
|
|
|